a contactor hired 150 men to pave a road in 30 days.how many mem will be hire to do the same work in 20 days​

Respuesta :

kevinmario2008 kevinmario2008
  • 05-12-2021

Answer:375

Step-by-step explanation:W = RTN

1 = 1/7500(20)N

1 = 20/7500N

1 = 2/750N

750(1 = 2/750N)

750 = 2N

750/2 = N

375 = N

There are 375 men to do the job in 20 days

Answer Link

Otras preguntas

heyy!! can someone help me out with this or give a answer? ty!
Many parts of the eye work to focus or control light except the... A.) Lens B.) Retina C.) Cornea D.)Pupil
does anyone know the answer
[tex]-2b-(-7)=11[/tex]
Please help me!!! 1. Convert 4mols H20 to grams? а 72g b 92g c 83g d 62g 2. Convert 4mols of H2O to atoms of H2O? a 1.4 x 10^24 atoms H2O b 4.1 x 10^24 atoms H2
SOMEONE PLEASEEE HELP, GIVING 100 POINTS FOR ANSWERS.
Mr Brown/ listen/ music/ now
The scale on the horizontal line axis is 5s per division on the vertical axis 9 m per division I need help with part 2
14 points and I will mark you brainiest if you tell me how to do it
What job Could aiming for when your marketing?